Dear All -

Can somebody explain the production order type for MTO variant configuration, settlement profile and settlement rule to be used.

regards,

Anupama

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 06:06 AM

    Dear Friend,

    For MTO also u can use same order type and order types are not dependent on ur scenario only u need to maintain statergy for the material in material master MRP view and this order type u r linking with prod. scheduling profile in OPKP with statergy and this scheduling profile u r assigning to a material in material master work scheduling view

    sree

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 06:13 AM

    Hi Anupama,

    MTO strategy is nothing to do with the Otder type.

    Same Order type can be used for both the strategies MTO / MTS. It is the Material Master MRP 3 view Strategy field will decide whether a Materials belong to MTO / MTS strategy

    You can maintain the order type dependent parameters to control the Order type procedure. You can also maintain the strategy in scheduling profile (OPKP) and assign the same in the Materials master Woek Scheduling view.

    Hope it is clear.

    regards

    radhak mk

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 06:33 AM

    Hi ,

    For MTO Scenario, the order type PP01 or any other order type nothing will be happened. You can maintain strategy group 20 in MRP 3 view in the material master and also you can maintain all Sales data views.

    Then you can run the transaction VA01 (Create Sales order) then you can run MRP by using t. code MD50 (Make-To-Order planning with Multi level). Finally You can run MD04 (Stock requirement list).

    In this MD04, Planned order & customer order will be appeared in the screen.

    This is the procedure for MTO scenario.

    Please let me any clarification.

    Regards,

    R.Mohan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 10:21 AM

    Hi,

    This is further to my earlier mail.

    You can use any Order type say standard Order Type : PP01 or Any other Order type which you have configured.

    For MTO scenario you need to maintain the Startegy type 20 in Materials MAster of FERT material and create the BOM / Routing (say Super BOM / Super Routing) and Object Dependencies.

    Create the Sale order and config the FERT material during the sale order creation for an item and save it.

    Run MRP in Tcode ; MD50 for the Sale Order Item, System will trigger the procurement proposals for the BOM items.

    Convert the planned order into production order and execute the order i.e perform teh confirmation / goods issue/ goods recipts for the order and then settlement is carried out.

    regards

    radhak mk

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.