Re: Manual Reorder Point

Dear All,

I am having a scenario where some of the components in the FG material BOM is subjected to consumption based planning.

Now When I am trying to run the MRP for the FG product, I can see the requirements i.e PR for Child items .But I cannot see the requirment for the child item which are subjected to CBP.

Now I do understand is that because of MRP type VB & not PD it is not appearing in MD04 screen.But

How to plan for this material.

Do I need to run the MRP individually for this material,If this is the case It would be very difficult for me to use this feature.

Please advice.

Regards,

Vivek

Add a comment
10|10000 characters needed characters exceeded

Related questions

7 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 04:18 AM

    Hi Vivek,

    Check the stock of the item which are to be planned with CBP......... if the requirement can be covered with the current stock then SAP will not generate any procurement proposals.......

    Thanks

    Kaushik

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Kaushik,

      Thnaks for the update. But for testing purpose I made a fresh Bom & rest.

      So on running the MRP there is no requirment for the CBP material.

      The stock is zero.

      Please Advice.

      Regards,

      Vivek

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 04:43 AM

    Hi,

    system will not plan for material which is having MRP type VB while running MRP for FG material.

    To plan these materials, run MRP for Total plant by MD01 or in background. So all the materials which are having MRP type VB will be planned.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 19, 2009 at 04:54 AM

    Hi Vivek,

    AS per your scenario, when you are running MRP for that FG (Single Item Multi Level) then system only pass the dependent requirement to that Component (say it is X), while for rest of the Child material is will generate Planing Proposal also.Reason is dependent requirement doesn't effect the planing file entry in the case of reorder point planning.It will change only in the case of stock fall below the reorder point, and activates the planing file entry.And during next MRP run you will get the planning proposal for the same.

    Regards,

    Dhaval

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 05:37 AM

    Hi Vivek,

    Please check whether the Planning File entry is there or not. Use T-Code MD21 to display the planning file entry for the material you are processing.

    If it is not there Create a Planning File entry for the material using the T Code MD20.

    It should solve the problem.

    Regards,

    Rohit.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 08:25 AM

    Hi,

    If you use the MRP type : VB system will not trigeer the procurement proposal unless the stock level falls below the reorder point. Check the stock if the existing stock is not sufficient to cater the reqt then only the system will trigger the reqt for CBP materials.

    As you said if you have created a new BOM with the new materials system will not show the reqt unless there is Some demand for the header material and the stock of the new child material is below the reorder level.

    If it is not rigger inspite of the material does not have stock, do the planning file entery for the new materials in Tcode : MD21 and and rerun the MRP.

    hope this will help you.

    regards

    radhak mk

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 01:34 PM

    Hi Vivek,

    for manual CBP items, you need to maintain a common MRP controller in material masters. create a background job of transaction MD01(or MDBT) with the MRP controller in user exit parameter field. you need to schedule this job daily. this MRP run will create procurement proposals independent of the MRP run for the FG/SFGs.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 13, 2009 at 02:56 PM

    Query resolved

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.