I have a problem in network.

I have created a network with some activities and I have given my material requirement in that network.

filed Res./Purc. req. is from release. Once I release the network, this filed is chaning to Immediately. I dont want this field to Immediatley.

Why this is happening? Is there any setting available for this?

Can any one please help me?

Thanks and Regards,

Praveen.

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

the field will change to immediately once you release

initially it set to on release

Whne you REL activity it will change to immediate

this is standard and expected behaviour

if you do not want immediately then do not release

Former Member
0 Kudos

Thanks for your reply,

Can you please tell me where we set this in IMG, I mean I fwant to set the option Never by defualt where to set this?

Regards,

Praveen.

virendra_pal
Active Contributor
0 Kudos

set in network profile

spro- ps- structures - networks -network settings - maintain network profile