Issue Relating to Power Cost

88 Views

Hi,

We have a scenario where we want to allocate service cost centers power cost to production cost centers. Service Cost centers are nothing but maintenance cost centers. But here in the plant maintenance order they are not confirming the power activity. But the units for power are obtained in maintenance order through measuring points. So can I take these units of power and allocate to product cost centers through development, so that product cost center power units include power units confirmed by production order and also power units allocated from maintenance order through abap development. Whether it is possible through development.Please suggest me.