Hi

Any report available which contains for a particular period the planned qty (planned order) the actual backflush qty and similarly for raw materials actual backflushed and planned

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Jan 17, 2009 at 09:44 AM

    Dear,

    MF12,MB51 for material documents (for movements 261) are only useful in this case.

    Otherwise develope the Z report.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 17, 2009 at 11:37 AM

    Dear,

    You have the Material Usage Analysis Report MCRO, here you can have the planned and actual qty of both finished product and components , you also have the period to analyze option where you can give your required range of dates.

    Thanks & Regards,

    Vijaya Bhaskar A

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.