Dear all ,

I have one item for which manual Pur Req has been created .

In MD04 Mrp stock requirement list able to see the Pur req

But if i go for ME57 the same is not available , why i am not able to see the same ?

regards

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jan 17, 2009 at 08:27 AM

    Dear,

    PR's based on some selection criteria so check it in ME57.

    Or also check through ME52N or ME53N

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.