6930 Views

Hi Experts,

I am a PS consultant. Created a cost center and activity type and then assign it to work center. But i am getting this warning message when i assign the activity type to work center;

--- "Activity type 1500 is not set up for cost center BP01 1100 in the year 17.01.2009

Message no. CR062

Diagnosis

You are attempting to allocate activity type 1500 to the work center. However, this activity type has not be set up in controlling area BP01 for cost center 1100 on 17.01.2009.

Procedure

Allocate an activity type to the work center that is set up for the cost center 1100 on 17.01.2009 or

setup the activity type you want in cost center 1100 within cost center accounting to 17.01.2009. Please remember, that both the assignment of a work center to a cost center and the allocation of an activity type to a cost center have validity periods." -


Please suggest and advise.