Hello SAP Gurus,
I have a problem with transaction CM21 when I try to change an operation from work center to another. The scenario is:
- WC01 (Work center)
- CC01 (Cost center)
- Activity A
- Activity B
- WC02
- CC02
- Activity C
- Activity D
In my production order I have WC01 in the operation 0010, I release order and save. Then I go to CM21 and I schedule the operation 0010 to WC01 and save, until now everything is good.
I change my mind and I go to CM21 and I change from WC01 to WC02 and I save.
When I make the confirmation in CO11N for operation 0010 the system shows a message of wrong cost calculations because I have changed the original work center in the CM21, and the Cost Center and the Activities Types are not updated...
Little help please...
Thanks in advance,
Adelmo Silva