Former Member
Jan 16, 2009 at 06:40 PM

[HELP] - CM21 Rescheduling work center.

163 Views

Hello SAP Gurus,

I have a problem with transaction CM21 when I try to change an operation from work center to another. The scenario is:

- WC01 (Work center)

- CC01 (Cost center)

- Activity A

- Activity B

- WC02

- CC02

- Activity C

- Activity D

In my production order I have WC01 in the operation 0010, I release order and save. Then I go to CM21 and I schedule the operation 0010 to WC01 and save, until now everything is good.

I change my mind and I go to CM21 and I change from WC01 to WC02 and I save.

When I make the confirmation in CO11N for operation 0010 the system shows a message of wrong cost calculations because I have changed the original work center in the CM21, and the Cost Center and the Activities Types are not updated...

Little help please...

Thanks in advance,

Adelmo Silva