hello PS experts,I have executed report CJ33 & S_ALR_87013558 for same WBSthere is a difference in overall budget of S_ALR_87013558 & current budget of CJ33.There is no supplement or revision done in budget.As suggest in some the old post in SCN, I have tried by running tcode CJEN & CJBN to reconstruct availability control but still that inconsistency exist in both report.requesting to all for suggestion.Thanks in advance.pradeep

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Nov 09, 2016 at 10:42 AM
0

Hi Pradeep,

There are numerous notes available in SAP for *558 report. You need to check whether any note is relevant for your issue.

Also, to analysis further check the entries based on tables RPSCO or COSS/COSP to check the exact posting. In case if some particular type of Budget is missing like Supplement etc, then check with 558 form to understand whether the value types are included.