Hi All,
My client is a manufacturer of a machining tools. Their production is purely based on the designs and specifications given by their customer. Once they receive the sales order based on customer specifications they will create a BOM. Depending upon the creticallity of the product they will release the Design documents in stages. Say for example the tool can be manufactured by performing 20 operations. Design dept will release the 1st drawing for 5 operations, 2nd drawing for next 10 operations and 3rd drawing for last 5 operations . Routing can only be decided once the drawing is released. WIthout waiting for the comlete drawings to get release for production, PPC dept will create a routing for 1 st drawing and will start the production similarly for 2nd and 3rd drawings.
How can we map this scenario in SAP.
Thanks