hello experts,
We have created a material with in house production time 15 days.
We don't maintian BOM and routing for this material but we have created reference operation set for this material.we have mentioned setup, m/c and labour time as 1, 2 & 5 respectively.
We have created plan for this material for date 4/02/09.After MRP run we got planned order and we convert this planned order into production order with the help of reference operation set.
Now the problem is start date for order is 3/02/09 instead of 18/01/09 considering one day holiday in a week.Order finish date is 4/02/09.
what's the solution for this problem.
regards,
sarfaraz