Hi,

I have a filling Line PL1. Capacity is 24 hours.On this we can process products A and B.I have defined rate routing and assigned to the production versions in the respective Material master. Now my requirement,

If the product A is processed on PL1,maxmum run length is for 24 hours and the machine must be stopped for cleaning after this time for 2 hours.If the product B is processed on PL1,maximum run length is for 36 hours and the machine must be stopped for cleaning after this time for 4 hours.A and B can be planned on the same filling line back to back without a major change over and the filling line can be used continuously for 36 hours.But B and A cannot be planned on the same filling line back to back without a major change over and change over is required.

How do we map in the routing and where we maintain the conditions of 24 hous max run lentgth if product is A and 36 hours max run length if product is B....

Thanks