    Posted on Jan 15, 2009 at 06:55 AM

    hi manish,

    01 and 02 are the checking group.

    Availability check is carried out with the help of these checking group and checking rule.

    Checking group 01 and 02 are maintained on the material master.

    01 - Individual requirement -For this system generates transfers the requirement for each order to the MRP .So that MM can either produce or procure.

    02- Collective requirement.-In this all the requirements in a day or in a week are processed at a time. System stores all request and passes on to the MRP in MRP run.

    Anil

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 15, 2009 at 06:57 AM

    Dear Manish

    a) Daily Requirements

    In the standard system, checking group 01 is set up so that daily requirements are passed on to production. This means that there is only one line visible in the stock/requirements list (as shown above) that contains the cumulated quantity for one day, rather than the individual sales orders. The sales order number does not display on the Order line in the stock requirements list.

    b) Individual Requirements

    A line for individual requirements is created in the availability overview for each sales and distribution document and schedule line. This line contains the order quantity and the number of the document which created the requirement as well as the item number and the requirements class.

    Individual requirements have the advantage that the initiating document can be identified (the initiating document is displayed in the availability overview for each requirement).

    thanks

    G. Lakshmipathi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.