Hi,
I need some clarifications about scheduling.
I maintained the following details for the Product in MM
GR =1 , Inhouse =1, Planned Deliver=1 and Scheduling Margin Key = 1 + 1+ 1 +1.
and In routing i have 2 operations Operation 10 setup time i have given 30mts and for Operation 20 i didint maintain any standard timings.
I have given requirement on 30.01.2009.
When i run the MRP on Basic Scheduling (MD02 - Scheduling indicator is 1)
Planned Order
Ord Finish 29.01.09
Ord Start 28.01.09
Pla Open 27.01.09
Pro Order (Basic Date)
Basic St 28.01.09
Basic Fi 29.01.09
Production Order Sch
28.01.09 14.20Hrs
28.01.09 15.00Hrs
27.01.09 (Release)
When i run the MRP on Lead Time Scheduling
Planned Order
Ord Finish 29.01.09
Ord Start 26.01.09
Pla Open 23.01.09
Pro Order (Basic Date)
Basic St 26.01.09
Basic Fi 29.01.09
Production Order Sch
27.01.09 13.55Hrs
27.01.09 15.00Hrs
26.01.09 (Release)
Can any one explain the dates how the system has calculated.
Thanks in adavance
Nag