Hello Sirs,

I have a requirement for following scenario......

I have a FERT which has 2 Components, 1 HALB + 1 ROH (Purchasing Item)

When i run MRP (MD02) for FERT, i want Planned Order for HALB + Purchase Requisition for ROH.

As at present when i run MD02 it gives me Planned Order for FERT, but nothing for the ROH.

Is it possible to get Pl. Or + PR !? If yes, please guide me with the required settings.

Thanks in advance,

Harris Panchal

Edited by: Harris Panchal on Jan 15, 2009 10:59 AM

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi Harris,

Yes it is possible.

Now if you are running MRP through MD02 then most imp Prerequisite is all the materials which includes both Header material and Component should contain MRP type PD,P1,P2 and not M0,M1,M2.

Also check below parameters also.

- In MRP 4 view of Header Material (FERT and Halb both) MRP for Dependent Requirements should be maintain as Materials for dependent requirements are planned (Blank)

- Check BOM valid From to TO date and also From to To Lot size of Fert code.

- If you are using Production version then check above parameters (checks no. 2) for production version also.

Regards,

Dhaval

Former Member
0 Kudos

Hi Dhaval,

Thanks for the answer. It worked there and then itself. Sorry for replying late.

Regards,

Harris Panchal