on 01-15-2009 5:28 AM
Hello Sirs,
I have a requirement for following scenario......
I have a FERT which has 2 Components, 1 HALB + 1 ROH (Purchasing Item)
When i run MRP (MD02) for FERT, i want Planned Order for HALB + Purchase Requisition for ROH.
As at present when i run MD02 it gives me Planned Order for FERT, but nothing for the ROH.
Is it possible to get Pl. Or + PR !? If yes, please guide me with the required settings.
Thanks in advance,
Harris Panchal
Edited by: Harris Panchal on Jan 15, 2009 10:59 AM
Hi Harris,
Yes it is possible.
Now if you are running MRP through MD02 then most imp Prerequisite is all the materials which includes both Header material and Component should contain MRP type PD,P1,P2 and not M0,M1,M2.
Also check below parameters also.
- In MRP 4 view of Header Material (FERT and Halb both) MRP for Dependent Requirements should be maintain as Materials for dependent requirements are planned (Blank)
- Check BOM valid From to TO date and also From to To Lot size of Fert code.
- If you are using Production version then check above parameters (checks no. 2) for production version also.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.