Production Scrap Process

Former Member
0 Kudos

Hello Guru's,

We are following discrete manufacturing process.We have an die casting material in which for A material we are maintain the BOM for child B and C. where C material is By product material(-ve value maintained). It is planned scrap 5% which is maintained as by product. When i am confirming the production order for 100 number for A , the 531 movement for 5 numbers in C has been posted automatically. But in my case sometimes the actual scrap percentage will increase compare to plan scrap.

In this scenario how i will book the actual scrap in the confirmation

Thanks in advance

Pugazhendi AS

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Prasath,

Screen variant placed for component screen not able to edit.

Former Member
0 Kudos

Hellow Jessica,

Thanks for your inputs. But in our case the goods movement screen is not editable. We have put the Screen variant on this.

Prasath
Contributor
0 Kudos

Hi Pugazh

As per my understanding,

You can maintain the actual scarp qty in production order components (-ve Sign qty),So that same quantity will be displayed co11n goods movement screen.

Please share the BOM and production order component screen

Regards,

Prasath E

jessica_li
Advisor
Advisor
0 Kudos

Hello Pugazhendi,

If you are using CO11N to execute confirmation, you can click "goods movement" button at left upper corner and enter/adjust the true Goods movement in next screen.

best regards,

Jessica Li