Missing operations and dummy activity in process order

Former Member
0 Kudos

Hi,

we currently maintain several alternate modes in PP/DS PPMs in APO.

When we create a planned order in APO, CIF to R/3, then do conversion to process order in R/3 everything is fine.

When we create a planned order in APO, CIF to R/3, then do conversion to process order in APO, all of the operations are missing and there is a dummy activity present.

We also noted this only occurs when the mode selected in APO by default uses a different resource than the one assigned to the PPM's recipe back in R/3. That is, if the recipe in R/3 uses resource LINE_01 and APO selects resource LINE_02 by default, the issue occurs.If the recipe uses LINE_02 and the APO selects LINE_02 by default, then everything is fine.

Has anyone seen this behavior before ?

Thanks,

Roger

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Roger,

Conversion of planned order in R/3 is manual conversion and can override every thing even though it is wrong..but APO does not let you do that.

I didn't understand "if the recipe in R/3 uses resource LINE_01 and APO selects resource LINE_02 by default".

isn't the order created by PPDS in APO? Then they should have the same resource.

I suggest you align the PPM and the R/3 resources in the production version. Is the integration model for PPMs running?

Former Member
0 Kudos

Hi Visu,

For right now, the planned order is created in the product view.

In R/3, the recipe has an operation which uses LINE_01 resource (let's say, production version is L1)

In APO, there are several alternate modes :

LINE_01

LINE_02

LINE_03

By default, when the planned order is created in the product view, the mode with the shortest duration is chosen. In this case, if I create a planned order using the PPM for production version L1, and LINE_03 happens to have the shortest duration, then the order is created for LINE_03. Since LINE_03 is not the resource used in the recipe for production version L1, we run into the issue I mentioned previously.

Coincidently, I also noticed that the R/3 process order type is set to schedule automatically.

When I go into edit mode on the process order operation, make no changes, but then save the order the correct resource and operations reappear in APO.

Regards,

Roger

Answers (2)

Answers (2)

Former Member
0 Kudos

For what it's worth, I was able to trace the issue back to a user exit implemented for process order change.

However, while investigating, I found out that operations might be dropped if the duration is zero, or the resource is not in an active integration model.

Former Member
0 Kudos

I think in recipe also if you defined the alternate resource line_l3 then system will not change the data while converting Planned Order.