Dear All,
Can you pls suggest how can we plan capacities for an activity of a project.
For example:
The activity to be performed is Painting.
Total quantity of work for the activity is 100 m2
duration of the activity is 10 days
Somewhere in masters, may be in work center capacity planning, can I
plan that for 1 m2 of painting the required capacities as:
Painter: 1 day
Mason: 1 day
helper: 2 days
ladder: 2 days
Painting Brush: 2 days
And when i plan the activity as above for 100 m2, can system automatically plan
the requirements as & also give the planned cost on the basis of this requirements.
Painter: 10 day
Mason: 10 day
helper: 20 days
ladder: 20 days
Painting Brush: 20 days
your valuable suggestions are required.
thanks in advance.
Regards,
VikasDev