Hi APO Guru's,

In our business process modelling Customer wants scheduling as per Product Priority. Customer wants to give a definite priority of products in which he wants the sequencing to take place.

So, we thought of giving Product Priority in SNP2 Tab and PPDS Planning heuristic and run squencing heuristic which should take care the Product Priority.

PPDS orders are getting created with priority that we can see in //RRP3.( Priority values are same as what we have maintained for products)

But to our surprise, could not find one which takes care priority while scheduling.

Scenario: Product A Priority 1 -demand on Last day of the Month, Product B -Priority 2 -Demand middle of the month, Product C -Piority 3 -Demand beginning of the month.

System should sequence the products like ABC, this is our expected output.