Actual Cost statistical 0(zero) on wbs

Hi experts!

I am facing a issue here: We have an asset being added to project, using statistical cost element, and I am being able to check the commitent on budget, during the PR and PO.

But when the MIGO is done, the actual value is 0, on any repory. I checked on COEP and there are 2 lines: a debit and credit.

Even the value is transfered to the asset, on MIGO, the statistical actual value(categ11) should stay on WBS reports, since the client wants to check the budget.

We are using HANA here, can anyone help me please?

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jun 11, 2018 at 06:22 AM

    Hi,

    Please ask your CO consultant to create Statistical Cost Element for the Inventory GL.

    Thanks