COM Routine error

Hello Friends,

We have a problem loading one particular CVC in planning book.

When we tried loading this particular CVC in planning book, we gor an error as "COM - Error unknown".

So we tried checking consistency for the planning book time series, that couldn't resolve the problem. so we deleted this CVC from the planning area and then we recreated the same.

At that moment that error got resolved. But one week after that we got the same problem with another CVC.

It seems this problem is recurring and at a time only one particular CVC is getting these error..

Could anyone please help me resolve this problem.

Thanks in advance.

Regards,

Jacky

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 15, 2009 at 04:02 AM

    Hi jacky,

    When creating the CVC are you checking the indicator "Adjust time series" or run the program /SAPAPO/TS_LCM_PLOB_DELTA_SYNC?

    Also ask your basis to check the COM build in your system.

    Regularly schedule the program /SAPAPO/TS_LCM_PLOB_DELTA_SYNC, consistency checks:/SAPAPO/TS_PSTRU_CONS_CHECK

    and /SAPAPO/TS_PSTRU_CONS_CHECK.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello Jacky,

      I recommend you to create the OSS ticket to the component 'BC-DB-LCA' to get

      the SAP support on this problem.

      Thank you and best regards, Natalia Khlopina

  • avatar image
    Former Member
    Jan 13, 2009 at 08:33 AM

    Hi Jacky,

    When you upload CVC, try to carry out in background and study the logs created. This will helps you to trace your unknown error. There could be possibilities of consistency check required at livecache itself. Carry out livecache consistency check and try.

    Please confirm.

    Regards

    R. Senthil Mareeswaran.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Senthil,

      Thanks for your reply.

      I am not aware of loading the CVC in planning book from background. Can you please elaborate on the same.

      We ran the live cache consistency program and it got finished sucessfully, but still the problem exists.

      Waiting for your reply.

      Thanks,

      Jacky.

  • avatar image
    Former Member
    Jan 13, 2009 at 12:35 PM

    Hi Jacky,

    If you goto Create characteristic combinations, after selecting your MPOS, then it will show the option of Generate in Background radiobutton, select that. In the same screen itself, you can view the logs.

    Regards

    R. Senthil Mareeswaran.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 13, 2009 at 10:45 PM

    Thanks Gurus.

    I tried reactivating the planning book and reloading all CVCs again in the planning book, and the error is solved. Still not sure what might be the reason.

    Anyways thanks to all for your responses.

    Regards,

    Jacky.

    Add comment
    10|10000 characters needed characters exceeded