offset functionality

Dear Experts,

Can any one clarify me:

In SAP PS we have offset functionality?

What is this function.....how it works?

Regards

Chandra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 13, 2009 at 05:20 AM

    Hi Chandra,

    Offset can be given to 1. relationship 2. activity element.

    For relationship offset refer this:

    http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/2261c746e611d189470000e829fbbd/content.htm

    For eleemt offset refer this:

    http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/22771746e611d189470000e829fbbd/content.htm

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 13, 2009 at 05:21 AM

    If u are refering to offset in Activity Element or Material View....

    Offset in Activity Element (Offset Start & Offset Finish)

    Offset between the sub-operation start and the corresponding reference date. Actiity Element start or finish date is offset from repective activity date

    Offset for Material (General Data)

    The activity-related time interval is used for the alignment of the requirement date in relation to the start or finish date of the relevant activity.

    You can use this time interval to specify lead times or follow-up times for the corresponding date.

    A positive time interval is equivalent to a follow-up time and a negative time interval a lead time.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear experts....

      Thanx .....Shri...Nitin.

      Congrats ........Venkat....

      Hey Nitin where u gone these days.....so busy.

      I have rewraded points to all

      Regards

      Chandra

      Edited by: chandrasai on Jan 13, 2009 6:31 AM

  • Jan 13, 2009 at 05:29 AM

    Use

    You can use this value to enter the lead-time offset for a component in relation to the start date of the operation to which the component is assigned.

    Integration

    The following application areas read the lead-time offset for an operation:

    Maintenance orders

    Networks

    Production orders

    Features

    You can enter a positive or negative value for the lead-time offset.

    For the detail you can refer this link.

    http://help.sap.com/erp2005_ehp_04/helpdata/EN/ea/e9b4464c7211d189520000e829fbbd/frameset.htm

    Regards