Error Message KD205 for WBS without actual cost

Dear experts,

I have WBS element with the following characteristics:

- marked as account assignment

- has been released

- doesn't have actual cost yet, therefore it doesn't have settlement rule

When I run the settlement (CJ88) for project which this WBS belongs to, an error message KD205 (Maintain the settlement rule of the sender) will appear

Since there's nothing from that particular WBS to be settled, is there any way to change the error message into warning message?

Thanks a lot.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 13, 2009 at 04:45 AM

    Hi,

    Tick the check box "Check trans. data" before executing CJ88.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 13, 2009 at 04:58 AM

    Dear Shrikant Rakate,

    Thanks a lot, it works!