Hi Experts,

I am trying to copy actual costs into plan values using transaction CJ9CS. While doing this, not all the actual costs are copied to plan values. Errors are as below

1) Primary cost element is not supported in secondary cost planning

2) Transaction RKPW cannot be planned for cost element category of 21

The actual costs on project are from some direct costs on WBS and maintainance order settlement on WBS. I understood that the direct costs(general postings) are copied into plan where as any settlements from other objects(in our case maintainance order) are not copied using CJ9CS.

I need all actual costs are copied into plan version 0. Is there any solution to this??

Regards,

Laxminarsimha

Accepted Solutions (0)

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

Please refer SAP note 407984. The part of Solution one is pointing to error you are getting.

Regards

Nitin