Asset in project.

Dear experts,

Asset in project.

We have many sub project officesu2026.with same profit cent:

Actually I want to know whether we can maintain one project for maintaining only for asset(I mean in project office Equipments,Machines,Vehicles).

.

Can any one explain me the process.(some inputs)

Regards

Chandra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 12, 2009 at 10:43 AM

    I hope u want know that from one project can we have multiple assets. Yes its possible.

    Venkat

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear Experts.....

      Venkat............Venu........Hemanth.

      Thanx for your inputs.

      Now i can discuss with my team.

      I have rewarded points to all.

      Regards

      Chandra

  • avatar image
    Former Member
    Jan 12, 2009 at 11:02 AM

    As Projects are temporary in nature, the costs need to be settled to some cost objects.

    The best way for asset maintenance is through Plant Manintenance. Project office assets can be maintained under PM and mapped to the project for cost accumulation.

    Or the Project offices can be different cost centres...

    you can give a thought on the above lines.