To populate profit centre when create Production Order

Former Member
0 Kudos

Hi All,

I having this problem... when i want to create Production Order against Sales Order i want to populate Profit Centre field with Value (Profit Centre that have in Sales Order) to production order.... so do you have any idea how i can get this.... maybe the user exit that can i use for this prob?

thanks ...

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Maintain the Profit Centre in Costing 1 View of Material Master.

Then it will be defaulted into the Production Order.

Or refre the OSS note 176012.

Regards,

R.Brahmankar

Former Member
0 Kudos

i already apply this notes... if ok when we do a normal process but when we do rework so they dont pickup the profit centre...

Former Member
0 Kudos

Missing profit center in rework order.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Rework order is assign to main order so why do you want profit center for rework order? As it is part of main order.receiver can be parent order or material or cost center. Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

I think there is a reason on this... thats why i need profit center value must be there. Maybe someone have an idea on this...

Former Member
0 Kudos

Some one can give any idea? cause i'm still struggling on this.... huh

Former Member
0 Kudos

Dear,

If you want to have the default profit center to flow automatically then you have to maintain it as a mandatory field in Material Master and then if you run the flow it will automatically bring in the value.

Thanks & Regards,

Vijaya Bhaskar A

Former Member
0 Kudos

i cant give profit centre field mandatory based on some requirements from user. Do you have any solutions? maybe SAP have user exit that we can used it?

i'm using CO07 to create the production order...after i key in and insert bla..bla..and enter i can maintain settlement rule...from this part in settlement receiver i select the order and also at this time i want profit centre value to populate to production order screen. So when i go back to production order create the profit centre is populate...

thanks.

Edited by: anuar jusoh on Jan 12, 2009 7:00 AM

Edited by: anuar jusoh on Jan 12, 2009 7:07 AM

Former Member
0 Kudos

Hi Anuar,

Have you tried creating the production order using co08 (production order w.r.t sales order) ???

Regards,

Vivek

Former Member
0 Kudos

in co07..i just key-in Production Plant and Order Type only for create Production Order.