availability check calculation after ATP

HI,

When the ATP run for a sales order the Material Availability Date, Loading Date, Good Issue Date in the scheduline lines are calculate again starting from the Requested Delivery Date and the Stock available.

I need to manage manully the Material Availability Date so do you know how can I avoid the Material Availability Date recalculation (to by-pass the satndard functionalities)?

Thanks,

Alessandro

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 13, 2009 at 11:22 PM

    Alessandro

    The following user exit may work for your purpose. You may access it by SMOD.

    SDTRM001 - Reschedule schedule lines without a new ATP check

    Roberto

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.