We have many production orders with a released status. The majority of these are not yet started in the factory. The user creates orders (in large numbers and puts them on a “released” status. Should she instead be keeping the order at “planned” status?
I have a labour code that is applied to all BOMs that has just had its standard rate increased. I presume the orders that are “released” in the system are going to use the old standard rate. Is this correct?
I would like the new rate to be made effective, so all these “released” orders should be picking up the new labour rate in the BOM.
Can you please confirm which rate will be picked up – the rate the production order was “released” or the new rate, given it will be “closed” after today.