Hi,
We have MRP active for materials. We have a batch job scheduled everyday for MRP run to create PR/Reservations for PM orders. While executing MRP run, system checks any open order is created or not even though the open order delivery date is after 9-10 months from current date. Because of which system creates reservation for the material.
In some cases, we need the material early (like in next 20 days) for PM order. Even though our inventory is zero, MRP run does not create PR, it creates reservation instead because few POs are available for this material with delivery date after 9-10 months. So the procurement team does not get information to buy the material immediately.
Our requirement is : Can we restrict the material availability check period to next 60 days in the MRP run so that system should check if any open PO delivery is available in next 60 days or not. If no open PO delivery is available in next 60 days, system should create PR for external procurement.
Please suggest.
Thanks
Satya