WIP customization

Former Member
0 Kudos

Hi!

When i am customizing for valuation methods for WIP ( transaction code: OKGC) and press new entries button, system is asking for actual costs or target costs, when i have selected actual costs, system is asking for controlling area,RA version and RA key. After entering this, system is giving error message " specify new values". I don't understand what it mean? I have to define valuation methods for different order status.

regas,

Ramesh B

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

t

Former Member
0 Kudos

Hi Ramesh,

How did you correct that problem..

even i am getting same problem when i am trying with RA key 00002..specify new values

but when i am trying with RA key 00003, it is setting valuation marthod properly..

Pls help

Former Member
0 Kudos

Hi!,

Please take care that when you are entering result analysis versions, system check if any entries already existed in that table, so make sure that no status is maintained for that version for REL, TECO,DLV etc., if already exists, system won't accept, then you need to remove all entries with result analysis verion, and again enter controlling area, result analysis version, system will update for all the 4 statuses the valuation methods.

regards,

ramesh b

Former Member
0 Kudos

note that you need to enter only controlling area,RA version & RA key, system automatically updates 4 statuses with valuation methods.

ramesh b

Former Member
0 Kudos

Hi

Pls note that, We use different RA keys for varied purposes, like RA KEY 00003 for Sales order cost WIP/RA calculation

RA00002 for WIP At Target cost which we will use REM (Product cost collector)

So it is recommended to define each RA key is own customising, like WIP at Actual cost or target cost, so that it will serve the required purpose, instead of using same RA key for different trasactions.

Former Member
0 Kudos

Production Order Status will the basis to calculate the WIP. Those are Delivered, Partially Delivered and Technically Completed.

Thanks,

VR

Former Member
0 Kudos

Yes each satus needs a valuation

REL

DLV

PREL

TECO

pts appreciated