on 01-08-2009 11:27 AM
Hi
Maintenance plan display screen IP03 and MP schedule screen IP10 are showing two different dates for the same next call of a plan. Previous call confirmation date is same in both TCs.
What would be the root cause for this.
Thanks for your reply in advace.
I'm actually just pasting the answer I received from SAP Support to the same question:
IP03 and IP10 has different logic. IP10 is based on live data, IP03 is historical (table MHIO and MHIS) and is based on when the call was last scheduled and saved. IP10 is a scheduling transaction, IP03 is a display transaction data must be saved in IP10 to update the call in IP03.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Transaction code IP10 is single maintenance plan schedule in system and date are showing as per your time based or performance based cycle frequency but IP03 is display of maintenance plan which have mentioned to start of cycle date and key date only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Response to reply from Peter Atkin: This seems to be a general issue as I have noticed quite a few times now that the dates differ in both IP03 and IP10. Our Maintenance Plans are always scheduled on first of every month using IP30. End-User have access to only tcode IP03. I came to know of this issue when end-user informed me that the next Planned Date in IP03 is not correct. For instance if last Order was TECO on 1-Jan-2013 and the frequency is 8 months then next Planned / Called Date should be 1-Sept-2013. In IP03 it does not show that but in IP10 (for which i only have access) shows the correct date.
Response to reply from Akhilesh: What exactly you mean by Cycle Date and Key Date?
Faisal
Hi,
The Dates will differ depends upon the Shift Factor Late/Early Completion. If you not complete the task with in the mentioned date. So you will be entering the finish date it may be +/- according to that the system will re-schudule the dates.
Regards,
Venkatesan Anandan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I find the above discussion very useful. I updated IP10 by pressing the Update Scheduling button and then saved the plan.
I then check the same in IP03 and it shows the same dates. So it works!!!!!!!!!!
Now my query is: As our end user only have access to IP03 and not IP10, they will always see the incorrect Planned / Called dates. Is there a way around?
Just a background: These calls are generated through IP30 and are scheduled on monthly basis.
Thanks
Faisal
HI
whne you see in IP10 system show which are going to schedule and if you delay order completionthen also date changes(if any shift factors maintained)
in IP03 you see alrady scheduled dates only
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please help me on this issue. Now i found that the subseqent start date is different in IP03, IP10 and IP24 as well. Please not that the dates are different only in the case that when the completion date is different than plan date. Practically it is always. Your immediate response will help me a lot. Thanks in advance.
Hi
Im providing with and example please..
X is the plan #
Now the date in IP10 is like this
Plan date Call Date Completion Date Due Pacages
16.01.2009 11.01.2009 3M
11.04.2009 02.04.2009 6M
10.07.2009 01.07.2009 3M
IP03
Plan date Call Date Completion Date
16.01.2009 11.01.2009
16.04.2009 07.04.2009
15.07.2009 06.07.2009
IP24
Main Plan Call No. Start Date
1 11.01.2009
2 06.04.2009
3 11.07.2009
Hope this information will help you to analyse and provide a solution. Thanks in advance.
Hi When i update the schedule it gets updated in IP03 or through IP30 system updates in IP03. But we do not want to do deadline monitoring every day. Is there any other way for IP03 to get update against confirmation. This is problem exist when the completion date does not equal to plan date. Thanks.
hi
once you enter the already scheduled plan ,then system will reschedule the plan and derive new dates based on the current reading,whereas in maintenance plan display it will display the previous scheduled one
whether your plan is time based or performance based .specify the details which will be useful for tracking
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.