on 01-07-2009 9:56 AM
Hi SAP Gurus,
Pls guide me how to apply substitution in PS, I want to do if i activate the Billing element in WBS then it RA and OH key must come automatcally.
Thanks in advance
Regards
Abhijit
Dear Abhijit
follow the Path
SAP Customizing Implementation Guide>Project System>Structures>Operative Structures>Work Breakdown Structure (WBS)>Maintain Substitutions
Define the following
1. Substitution
2. Applicatn area
3. Callup point
Create
Step 001 (Description as) Activate the Billing element in WBS
Select
Prerequisite:
as
Billing elem. = 'X'
(PRPS-FAKKZ)
and in
Substitution:
RA Key Constant value XXXXX
Overhead key Constant value XXXXX
Check the same by creating a new project..
Regards
Vikat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhijit,
please use this link :
http://help.sap.com/erp2005_ehp_04/helpdata/EN/eb/13796243c411d1896f0000e8322d00/frameset.htm
and do refer the SAP Note 440186 - FAQ 2: Validation and substitution in the project
Thanks,
Dhruv Kumar Malhotra
Edited by: Dhruv Kumar Malhotra on Jan 7, 2009 11:48 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
T code- OPSN
Prerequisite:
Billing elem. = 'X'
(PRPS-FAKKZ)
Substitution:
RA Key Constant value XXXXX
Overhead key Constant value XXXXX
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.