Hi SAP Gurus,

Pls guide me how to apply substitution in PS, I want to do if i activate the Billing element in WBS then it RA and OH key must come automatcally.

Thanks in advance

Regards

Abhijit

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Abhijit

follow the Path

SAP Customizing Implementation Guide>Project System>Structures>Operative Structures>Work Breakdown Structure (WBS)>Maintain Substitutions

Define the following

1. Substitution

2. Applicatn area

3. Callup point

Create

Step 001 (Description as) Activate the Billing element in WBS

Select

Prerequisite:

as

Billing elem. = 'X'

(PRPS-FAKKZ)

and in

Substitution:

RA Key Constant value XXXXX

Overhead key Constant value XXXXX

Check the same by creating a new project..

Regards

Vikat

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Abhijit,

please use this link :

http://help.sap.com/erp2005_ehp_04/helpdata/EN/eb/13796243c411d1896f0000e8322d00/frameset.htm

and do refer the SAP Note 440186 - FAQ 2: Validation and substitution in the project

Thanks,

Dhruv Kumar Malhotra

Edited by: Dhruv Kumar Malhotra on Jan 7, 2009 11:48 AM

Former Member
0 Kudos

Hi

T code- OPSN

Prerequisite:

Billing elem. = 'X'

(PRPS-FAKKZ)

Substitution:

RA Key Constant value XXXXX

Overhead key Constant value XXXXX