Hi

We have a strange issue with regard to Product allocation.

We have 3 keyfigures in our product allocation planning book.

Planned allocation Quantity,Confirmed allocation Quantity and remaining allocation Quantity.

Normally during ATP check on sales order, if the quantity in sales order is < = remaining allocation Quantity, the quantity is confirmed and the confirmed quantity is updated in keyfigure "confirmed allocation Quantity".

Now we have a problem that the quantities in keyfigure "confirmed allocation Quantity" is far high than planned allocation quantity keyfigure. Also if we check the incoming order quantity in ECC it is not real and the quantity is very less.

I dont know from where it is updating such wrong quantities in keyfigure "confirmed allocation Quantity"

Did any one came across such type of issue.

If so please share and help me in this regard.

Thanks in advance

vijaya

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jan 07, 2009 at 10:54 PM

    Hi Vijay,

    Check product allocation situation in /sapapo/ac42. it will show you product allocation qty, confirm qty and remaining qty for each period.

    duble click on the confirmed qty which will give you list of orders under that. If there is mismatch in total qty in orders and confirmed qty then there might be inconsistency in the Live Cache.

    if that is the case then try running /sapapo/OM17 for product allocation. it should capture incosistency in report. Then you can correct incosistency in the LC to resolve the issue.

    Regards,

    Harshil Desai