Converting CJI3 Standard Output to internal table in zprogram then updating all information in customized database table .

Here I am facing issues to get Current year commitments and previous year commitments for project related amounts.

I have WBS Element and Purchase Order Numbers in the internal table.

kindly suggest me to get all those amounts.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 13, 2017 at 11:07 AM

    Dear Rakesh,

    If you are developing new report, and as you said you have WBS, then fetch folloing value in internal table from RPSCO

    Just Pass WBSE to Table PRPS field POSID to get OBJNR. Then pass OBJNR to Table RPSCO field OBJNR & "21","22","23","24","26" to WRTTP. Get All the Values in Internal Table.

    now play with values as you required using filter with fiscal year to field GJAHR.

    Regards,

    Omkar Deshpande

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 14, 2017 at 10:45 AM

    Dear Rakesh,

    As mentioned by Omkar, You have to pull all Comm. values with the help of value Type and the values will be in year wise.

    Thanks,

    Mohammed Dawood.