on 11-08-2016 12:15 AM
Converting CJI3 Standard Output to internal table in zprogram then updating all information in customized database table .
Here I am facing issues to get Current year commitments and previous year commitments for project related amounts.
I have WBS Element and Purchase Order Numbers in the internal table.
kindly suggest me to get all those amounts.
Dear Rakesh,
As mentioned by Omkar, You have to pull all Comm. values with the help of value Type and the values will be in year wise.
Thanks,
Mohammed Dawood.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rakesh,
If you are developing new report, and as you said you have WBS, then fetch folloing value in internal table from RPSCO
Just Pass WBSE to Table PRPS field POSID to get OBJNR. Then pass OBJNR to Table RPSCO field OBJNR & "21","22","23","24","26" to WRTTP. Get All the Values in Internal Table.
now play with values as you required using filter with fiscal year to field GJAHR.
Regards,
Omkar Deshpande
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.