How to Calculate the days where Contract start 31st of the month

55 Views

Hi,

I am making a lease plan for One Year.

If I am taking the starting date as 20th of any month or any other date (except 31st) system is taking the end date of the next yr correctly .i.e.19th of next year.( we have taken the Calculation method " 30 days of Every Month".

but when I took the start date as a 31st of any month then system is not taking the Lease end date as 30th of the next year.

What can be the relevant reason for this.How can I change the Calculation Method in the Current lease Out Plan.

Waiting for suggestion