i have doubt with unbilled labor cost for particular project.
My client requirements : unbilled project cost it comes from 4 place.
1. Material committment cost (CJI5). only open items .
2. Billing document created but not yet released.
3. unbilled labour cost.
above 2 points are ok.
how i will get unbilled labour cost.
from CATSDB table i extract unposted labor hours. then how i will convert this hours to cost?