result analaysis+ Sattelment

Dear All,

I need to do result analaysis and i've configure it. As i've done KKA2 and the valuation method i've used is 01 revenue based. Now the problem is that as the actual cost is comming by GI is showing and COS is showing by GI so no inventry value is showing in result anlaysis.If actual cost as result of GRN is more then cost by GI then resulting value should be shown in inventory .

Now i am satteling the project i've made top WBSE as billing element and RA key to that only .As result of CJB2 is showing Results analysis key is not used for results analysis.

How can i sattel the project with this situation?

Regards.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jan 01, 2009 at 05:56 AM

    Hi Sukhveer,

    CJB2 is for creating a settlement rule for a period.

    With this , Settlement receivers will be appended to the WBSE master data.

    Actual settlement does not happen for this transaction. For Settlement use transaction CJ88.

    Hope this helps,

    Pradyumna

    Add comment