Currently i'm trying to explore the Procure to Pay process mining using celonis...

i'm new to ECC... I just want o know what are the "PO" are created on the basis of "PR" and "RFQ" and also which "PR" are going for the RFQ and contract creation.

By using EBAN table, which field can i use to filter these types .

Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 24 at 12:31 PM

    Your question is hard to understand, I hope I got it. You always have to look into the target object to find the reference, since one RFQ could be referenced in 20 POs. Or one PR could be used to create 20 and more POs.

    If you look into EBAN then you may find the status that a PO was created, you also find the last PO. But reliable is only the other way around looking at PO table EKET to get the referenced PR. Or PO table EKPO to find the reference to a RFQ.