Hi SDNers,

If you look into the Tcode MD01 MRP Run.

MRP is executed based on the material.

I want to execute MRP based on the MRP controller.

Now on MD01 there is a frame called as 'User Exit select material for planning'

Now here we select the user exit from the user exit key field.

There is also a user exit parameter field in this I want to enter MRP controller and based on this MRP controller the MRP should run.

i e only those material based on a particular MRP controller should execute.

How do we implement this logic in the enhancement M61X0001.

Regards,