cancel
Showing results for 
Search instead for 
Did you mean: 

Distribution method didn't transfered to ERP

rafalem
Discoverer
0 Kudos

Hi,

We use SRM 7.0 ECS and have a problem with account assignment distribution.

On SRM PO document contains a multiple distribution by amount.

On ERP same PO has a multiple distribution by percentage.

I tried to re-transfer PO to ERP to change distribution. Due to system cannot recognize difference between ERP and SRM we changed indicator in BBP_PD_PO_FLTER_UNCHNGED_ITEMS manually but the distribution was still same.

Any ideas ?

Accepted Solutions (0)

Answers (2)

Answers (2)

rafalem
Discoverer
0 Kudos

Hi,

Thanks for the answer. Yes the issue happens in service PO.

Unfortunatelly LOG_MM_MAA_1 is enabled and system landscape in table BBP_BACKEND_DEST is set as ERP_4.0.

Do You have some other ideas ?

Regards,

R.

summer_wang
Contributor
0 Kudos

Hi,

I assume the issue happens in a service / limit item.

In case of external classic scenario the value distribution in the account assignment for service/limit items is supported after the Multiple Account Assignment (LOG_MM_MAA_1) business function is activated in the ERP system.

Please check whether the function is activated in your ERP system.

Please see the SAP Notes

2041308- The quantity based accounting distribution lines converted to percentage distribution in the ECC system for service items

2099791- Value based account assignment is converted to percentage during the transfer of an extended classic Purchase Order