Transfer planning data to demand management/ planning data aggregation

82 Views

Hi there

in our planning scenarion we load the rough-cut plan into SAP based on product groups. After the load the planning data is transferred onto demant management based on product group definition, members and proportions defined in MC86.

We have a situation where one material MAT_1 can belong to two product groups, PG_A, PG_B. For the transfer of planning data into demand management, we use a mass function executed via Job, MC8G transaction.

Now the problem what we have since material MAT_1 belongs to 2 product groups. When the planning data for first product group PG_1 are disaggregated into demand management it creates planned independet requirements in active version 00. Eg. 10000 PC for MAT_1 each month.

When the second PG_2 group is processed it overwrites the numbers for

MAT_1 based on the PG_2 planning data. Eg. 5000 PC each month.

Our goal is to achieve following: When Material is available in more than one product group and planned data are transferred into demand management, SAP should aggregate these quantities and after job, the material MAT_1 should have total planned ind. requirements 15000 PC in each month there.

Is that possible to achieve this in SAP?

What is the setting which is relevant for this?

Kind regards

Juraj