Hello
I'm getting wrong figs in PS standard reports for Budget, plan cost and actuals.
Details are as below :
Company Code Currency(Object Currency) = EURO
Controlling Area Currency = INR
Translation Key which i use = M ( Mean rate as of today )
We in our organisation maintain the exchange rate on weekly basis.
My problem is that suppose i have a budget amount say 100 EURO then i cannot see the same amount in budget report when i convert this report in EURO. Same for Actuals and Commitments.
Since all the standard reports are by default in Controlling Area Currency i have a problem in viewing figs.
I have a solution on this which suggests me to make this report in Object Currecny by default, I want to know if any other work around is there.
Regards
Ashish