Hi Gurus,
Profit center is assigned to cost center and cost center is assigned to WBS element.
and WBS element is assigned to maintenance order as account assignment category in the additional data tab of the maintenance order.
I have assigned the spares in the order and when i do the MIGO_GI system is picking the dummy profit center always.
and we want it should hit the cost center(of WBS element), which in turn should hit the relevant profit center.
any posting to the dummy profit center is restricted from FICO side, due to which system is giving error.
I hope my explanation is clear.
Please suggest the solution.
Rgs
Pankaj
Hi Pankaj,
Check what profit centre is assigned to this particular WBS element in assignment tab or to project header at basic tab.
is there dummy PF is maintained?
Regards
Abhinay Gautam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.