on 12-23-2008 9:07 AM
Hello Guru,
We have some issue, our material 15330 finished product has a BOM of 10002100, but when doing a purchase order with
this finished product it did not explode in the line item of the purchase order. as we check this 15330 its BOM
usage was 7 (Empties-Returnable materials) and it was still in status 01.
why is this material not exploding BOM? where could we check where this problem could be solve?
Thanks
In Subcontracting, item category L enables Components ( BOM items) below level of the Fisnished componenet i.e at item detail level of individual line item.Don't confuse Item level and item detail level.
and don't expect the bom items at Item level.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ryan,
The lead time you might have given in Inforecord / Material master caused the problem.
Change the delivery date and check it will work
Regards
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This error will happen due to the problem in delivery date in PO.
Change the delivery date after the system gives the error message"not possible to determine components". Now try to explode the BOM in Materia data tab.
If still the components are not determined,create a PR for the same material where that problem wont arise.
then create PO w.r.t. PR,so all the components data will be adopted and you can save the PO w/out the error message being displayed.
Regards,
Deepak.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.