Dear all ,

for one production Order i have Checked all 4 required materials were available .

Released the same and goods issue Mb1a 261 is carried out .

Now , Out of 4 required material 1 material reversed 262 and issued to another Order

Now after reversing the same the material avaibility is checked for the same order for which reversal is carried out , Now still showing Material is Available for the same whr the same reversed and issued to another Order?

Regards ,

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 23, 2008 at 08:28 AM

    Hi Venky,

    If you done the reversal through MB1A it will not reflect the same in the production order component overview.

    Regards,

    satyajit

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.