Skip to Content

Table for Order

Hi All ,

In which table i could get actual start date & time and actual finish date & time for the orders.

regards

sunil

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 23, 2008 at 07:00 AM

    DEAR SUNIL

    Please check it in AFKO table.

    Fields are as follows

    GSTRI - Actual start date

    GETRI - Atual Finish Date

    Regards

    Makarand

    Edited by: Makarand B. Gurjar on Dec 23, 2008 12:41 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 23, 2008 at 07:09 AM

    Sunil Ji,

    AFKO(order Header Data) as also told by Makarand.

    Saurabh.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 23, 2008 at 08:05 AM

    HI

    check the table AFKO

    enter the order no. AUFNR

    and get teh details of Basic finish dateGLTRP Basic finish (time)GLUZP

    Basic start dateGSTRP Basic start time GSUZP

    get also from table VIAUFK_AFVC

    -ashok

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.