on 12-22-2008 1:31 PM
Hi.!
What are the setting I have to maintain so that delivery schedules are transmitted OR used for particular month not beyond that.(means not required to continue for next month.)
Thanks and regards,
Prashant
Hi,
You can limit the validity to date (e.g. 31.12.2008) you want in "Source list" via t-code ME01, then after 01.01.2009 system will generate the planned orders instead of the schedule lines in SA.
Regards
Tao