Hi,

What is commitment Item in Cost Centre. We requirement to show some commitment items in cost centre.

So kindly provide what the steps need to do for posting some commitment items into cost centre.

Regards,

Venkat

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 12:55 PM

    Dear Venkat Reddy,

    this is comming from FI at the time of posting, if the Found Management is Active.

    Regards

    radha

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello,

      Also make sure that your commitments are not being locked on your Cost Center.

      These settings are inherited from your cost center category.

      OKKP: Activate Commitment Management

      KS02: Make sure commitments are not locked.

      When a purchase order is prepared with account assignment COST CENTER, a commitment will get creaeted (In business terms, the company is committed to the outside party to purchase at least this much amount in the future). When the goods are being received from the outside party, to that extent the commitment gets reduced and will be posted to the actual.

      Thanks,

      Ravi

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.