very imp MRP

HI EXPERTS,

1)iam creating a material with 4 mrp views and i selected automatic reorder point planning with fixed lot size proceedure .while saving the data iam getting a error message which says that i need to maintain forecasting data.so my question is why should i require to maintain forecasting data when iam creating a material with automatic reorderpoint palnning

please answer my queery

2)for non stock materials like milk in canteen

it is understood that the stock is not held in inventory because of immediate consumption but why cant the cost is assigned

u know the price of milk and the quantity u procured and u easily find out the cost of consumption

thank u very much

regards meena

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 10:27 AM

    Hi Meena,

    1 ) If you creating MRP 4 views only system will not ask for the Forecast data provided you have not selected Forecast view In Select Views screen.

    2) If you want to have the cost of consumption of Milk --- Create Milk as a stock material and assign it in the BOM of the Header Material.

    Regards

    Raju

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 10:28 AM

    Hi,

    1.For automatic reorder point you need to maintain the forecast value, then only the system will calculate the reorder point value.If you select the mannual reorder point, then no need for forecast value.

    2. Coming to next issue i am not sure why the costing is not maintain in the non stock material.But if you want to include those views for non stock material type, you can maintain through OMS2.

    Hope it will be helpful.

    Regards.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 11:45 AM

    Hi,

    1. To calculate the automatic reorder point system needs the past consumption data & also the future requirements which will compare the past consumption data .

    So for this you need to maintain the Forecasting data also in the Material master.

    2. It depends on the material type you select for creation of materials.

    As per the standard SAP for non stock items we will not create the accounting & costing view for the material, it will always be the account assigned purchase.

    If you want the value also you can maintain the Milk with other material type like HIBE --Operating supplies which is a consumable & can maintain the price in the material master & also can check the consumption values for that.

    rgds

    gsc

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.